Targetprocess: Enter Team Capacity and Velocity

Capacity is the estimated amount of work a person or a team can accomplish in an Iteration. This estimation is based on each individual's agreed upon commitments to operational and planned work, while factoring in non-work time such as vacations and training.

Velocity is the average number of Story Points a team has historically completed per iteration. When a team is newly formed, typically the Capacity is also entered in the Velocity field, as a starting guideline. After a team has been doing scaled Agile for a PI, the team can then determine its Velocity for future iterations.

Entering Capacity and Velocity to an Iteration

  1. Navigate to the Team Iterations view. 
    • Expand Teams, then Team Overview, then select Team Iterations from the left navigation menu.
  2. Filter by the appropriate Portfolio and Team, if needed.
  3. Select the correct Iteration to open it.
  4. Expand the Info section on the right.
  5. Enter the team's estimated Capacity and Velocity. 
    • The Assigned Effort is automatically calculated by adding all the Story Points for each Story in the Iteration.